Client: Energy Development Corp.
Address: Ortigas Center, Pasig City
Project Type: Corporate Office
Project Completed: 3Q 2011

Energy Development Corp.

Energy Development Corporation required a new corporate office and occupied 7 floors of the 54 storey One Corporate Center in Ortigas Center. The project required the full fit-out of the bare office space of 10,000 square meters including a data center.

CLIENT REQUIREMENTS

Quantity Solutions Inc was hired as the QS & project manager to provide management directions to complete the project within the 3.5 months schedule. The project site was turned over as a bare concrete shell with glass windows. Construction team must deliver the furniture, architectural construction and MEP&F components within the construction period.

OUR CONTRIBUTION

Since the 54 storey building is already operational, construction activities must not affect the operation of the other tenants in the building. Working round the clock with precise planning, QSi deployed its 4 man team headed by Arch Leo Retardo and led the contracting party, Don Pin Corp, in delivering the project within schedule, budget and quality.

Quantity Solutions Footer Logo
QSI is committed to a zero-tolerance policy towards bribery and corruption. We actively enforce strict anti-bribery measures across all levels of our organization. Communicate any anti-bribery violations confidentially at abcc@quantitysolution.com
Contact Information
   Philippines
5F Southkey Hub 2, Indo-China Drive, Northgate Cyberzone Filinvest, Alabang, Muntinlupa City 1781 Philippines

USA
304 South Jones Boulevard Unit 3286 Las Vegas, Nevada 89107
Copyright 2024 © Quantity Solutions Inc. All rights reserved.